Time Schedules

The system uses time schedules to support access levels, local linkage, and automatic override modes for readers, monitor points and control points. These schedules are used concurrently and a change to a time schedule immediately affects any cardholder (via the access level), control point, reader, monitor point, or other user defined actions in local linkage.

 

 

The software supports 64 time schedules with 50 intervals for each NXT controller. Typically, different time schedules are defined for various groups of people such as employees, managers, janitorial staff, security, etc. These time schedules are then assigned to corresponding access groups.

 

 

Note:

 

 

The Time Schedules Window

From the Home Tab, click the icon and the Time Schedules window appears.

 

Time Schedules Window

 

There are three default time schedules.

 

Default Time Schedules

 

The first two schedules cannot be deleted from the system.

 

 

There is also one time schedule (Work Week) that can be used as is, edited to your specific needs, or can be copied and edited.